| 1. |
INTRODUCTION |
| 1.1 |
The Airtrack Scheme |
| 1.1.1 |
Airtrack is a proposal to provide rail access to Heathrow from areas to the west and south. Connection to the existing rail network is achieved by constructing a new link from the airport to the London Waterloo line at Staines. The scheme has been promoted jointly by BAA and Railtrack. It is shown on Plan 1 and described in Section 2. |
| 1.1.2 |
Consent for the scheme is proposed to be obtained by means of an order under the Transport and Works Act 1992. This will need to be supported by an Environmental Impact Assessment of the project. |
| 1.1.3 |
The timetable for the scheme is affected by the timetable for Heathrow Terminal 5 into which the railway is proposed to connect. Although permission has been granted for Terminal 5 it is not expected to open before 2008. The scheme is included in the Strategic Rail Authority's Strategic Plan for the rail network in which it is identified as a scheme for further development but for which there is unlikely to be sufficient funding or technical resources available to support implementation before 2010. The plan adds that if increased funding becomes available it may be possible to make progress more quickly and states that co-funding with BAA will have a major role to play in implementation. |
| 1.2 |
Impact on Spelthorne |
| 1.2.1 |
The whole of the new stretch of track, apart from the section below ground north of M25 Junction 14, is in Spelthorne. While communities over a wide area, including Spelthorne, stand to benefit from the services that could operate the great majority of the environmental impacts of the new line and its construction fall on the Borough. |
| 1.3 |
Purpose of the Brief |
| 1.3.1 |
The Council is aware that work is underway on developing the Airtrack scheme and this Brief has been prepared to give guidance on issues affecting Spelthorne that need to be addressed in its development. The Brief does not aim to list the national and regional policies relevant to the overall assessment of Airtrack. The Brief aims to set out the planning and environmental issues that should be examined including relevant policies, potential impacts that should be examined and potential opportunities that should be explored. |
| 1.3.2 |
The Brief purposely does not express a view on the overall merits of the scheme. The Council will make a judgement on the scheme as a whole once it has seen the overall proposal in its final form. It expects the developers of Airtrack to take the provisions of the Brief into account in finalising their proposals and it will in turn take the Brief into account in its assessment. |
| 1.4 |
Structure of the Brief |
| 1.4.1 |
The Brief is arranged as follows:-
|
| 2. |
OVERVIEW OF THE SCHEME |
| 2.1 |
This section describes the general form of the scheme from south to north. While there have been previous studies showing detailed alignments, both within and north of Staines, (see Section 3 below) those do not necessarily represent the final scheme. The physical works described in the Brief are those likely to be proposed but other options may come forward after further analysis and those will need to be considered by the Council as part of its formal consideration of any future Transport and Works Act proposal. |
| 2.2 |
The proposed route is shown on Plan 1. It commences in Staines town centre. A new section of track is proposed that would run alongside South Street connecting the Reading and Windsor lines. North west of the junction with the Windsor line a new station could be provided to the north of the High Street close to the Iron Bridge. The SRA consider the station should be regarded as an option at this stage but Spelthorne sees the second station as essential if the Airtrack scheme goes ahead. |
| 2.3 |
At the northern edge of Staines the Airtrack route turns off the Windsor line to run north across Staines Moor broadly following the route of a former railway embankment. It then continues north following the eastern side of the M25 until it reaches the Borough boundary at Junction 14 dropping below ground level and into tunnel at about this point. |
| 2.4 |
North of the Borough boundary the route turns east, remaining below ground level, to enter Heathrow from the west through the Terminal 5 site. |
| 2.5 |
The scheme will enable rail services to access Heathrow from the south and west and from London Waterloo all via Staines. Services are likely to run through Heathrow to connect to destinations to the north and east. |
| 2.6 |
The Strategic Rail Authority advise that decisions on service pattern and frequency have not yet been made. They add that it is likely service patterns will comprise 6 to 12 trains per hour in each direction on the Airtrack route from Staines northwards. These services could operate over an 18 hour day between 6am and midnight. A proportion of these services are expected to stop at the proposed new High Street station (see para 2.2). |
| 2.7 |
The scheme as so far proposed appears to give rise to potential impacts on the Borough which are examined later in this Brief. The major categories of potential impact (positive and negative) are:-
|
| 3. |
HISTORY OF THE SCHEME AND ALTERNATIVES |
| 3.1 |
History |
| 3.1.1 |
The London Waterloo line passes within 2km of Heathrow and the idea of a rail link connecting it with the airport has been attracting interest for many years. Plan 2 shows the schemes referred to in this section. |
| 3.1.2 |
In the late 1960's powers were obtained by British Rail to construct a southern rail link to Heathrow but this scheme was never built and the Underground was extended to the airport instead. |
| 3.1.3 |
At the Heathrow Terminal 4 public inquiry in 1979 the option of a link to the Waterloo line was considered as a possible means of providing rail access to London. This was rejected in favour of extending the Underground to the new terminal. |
| 3.1.4 |
At the Airports Inquiries in the early 1980's the prospect of a fifth terminal at Perry Oaks to the west of Heathrow Airport was first raised. It was suggested that a rail link could be provided into the airport through the site with a connection to the south but at that time Terminal 5 was rejected as a proposal and the rail link project did not proceed. |
| 3.1.5 |
A possible rail link to the south was considered again in studies in the late 1980's that led to the construction of the Heathrow Express connecting the airport to central London. By then the concept had been taken up by a group of Southwest London authorities and, in the Heathrow Express Bill, an undertaking was given that safeguarding would be included for a southern link to connect to the Heathrow Express. The southern link promoted by the South West London authorities, currently under the SWELTRAC label, envisages a link into the airport via Terminal 4. The new rail link would leave the Waterloo line between Ashford and Feltham and would follow a mostly underground route into the airport. A detailed study of the scheme including with and without Terminal 5 options was carried out in 1996. |
| 3.1.6 |
The HASQUAD (Heathrow and Southwest London Quadrant) Study in 1993 recommended new road and rail links to improve orbital movements in southwest London and improve connections from the southwest quadrant to Heathrow. Two rail options were identified, the first option was similar to the SWELTRAC route while the second option entered Heathrow from the east. The HASQUAD proposals were not taken forward following public opposition to the road proposals. |
| 3.1.7 |
The launch of the current Terminal 5 proposals in 1993 led to renewed interest in rail access to Heathrow via the Terminal 5 site. In 1995 a consortium including BAA and British Airways launched "The Western Connection" which involved a north-south link between the Waterloo and Great Western main line. The preferred alignment for the southern part is similar to that of Airtrack. Access to the airport would have been from an interchange outside the airport to the west with the possibility of a direct connection as a second phase. |
| 3.1.8 |
The Government-funded London Airports Scheme Access Study (LASAS) looked at alternatives for improving public transport access to Heathrow including various options for a southern rail link. It recommended for further study what it described as the "Runnymede Route", a scheme following the Airtrack route. |
| 3.1.9 |
Both the Western Connection and LASAS studies had raised the possibility of constructing the "Staines Chord" in Staines Town Centre connecting the Reading and Windsor lines (see para 2.2). The chord existed until the early 1960's but the area has been substantially redeveloped since removal of the track and the embankment on which it was laid. The technical feasibility of this proposal was confirmed in a 1996 study which also looked at options for a new station in view of the fact that the chord bypasses Staines existing station. The study found that relocating the station on the chord (approximately opposite the existing bus station in the town centre) would not be acceptable for safety reasons and instead suggested an additional station to the north of the High Street adjacent to the Iron Bridge. This was followed by a BAA-commissioned study of the environmental issues raised by the chord. |
| 3.1.10 |
The most recent published study was carried out in 1998 by a consortium including BAA, British Airways, Railtrack and a number of local authorities, together with the consultants HALCROW. This identified a possible detailed alignment for Airtrack. It also suggested that reversing facilities at Staines Station with new sidings might be an alternative to the Staines Chord, although this option has been criticised on the grounds that it unduly constrains capacity. |
| 3.2 |
Alternatives |
| 3.2.1 |
The Environmental Impact Assessment Regulations require assessments to consider alternatives to the proposed scheme. It can be seen from the review above that there are alternatives to Airtrack that could provide rail access to Heathrow from the south. |
| 3.2.2 |
The Council expects the Airtrack Environmental Impact Assessment to include an extensive and robust comparative assessment against alternatives. This should include two specific alternatives:-
|
| 3.2.3 |
This list of alternatives is not intended to be exhaustive and the promoters should identify and examine other alternatives as part of the EIA process. |
| 4. |
BREAKDOWN OF THE ROUTE |
| 4.1 |
For the purposes of considering specific issues raised by the scheme, the Brief breaks down the Airtrack corridor into four segments as shown on Plan 3. These are:-
|
| 4.2 |
Each segment is examined by reference to:-
|
| 4.3 |
The list of impacts and opportunities is not necessarily exhaustive or final. The promoter's studies may reveal other potential impacts that should be assessed and they may also reveal other potential opportunities. However, the Council will expect the issues identified in this Brief to be fully explored. |
| 5. |
THE STAINES CHORD SECTION |
| 5.1 |
Description |
| 5.1.1 |
The proposed route is shown on Plan 4, which also highlights issues and opportunities in this section. |
| 5.1.2 |
The Staines Chord turns off the Reading line in Staines town centre near the junction of South Street and Westbrook Road and then follows a curved route parallel to South Street joining up with the Windsor line just south of the Iron Bridge over the High Street. |
| 5.1.3 |
The route would be elevated about 4m above existing ground level. |
| 5.1.4 |
The route crosses land that is currently used as part of the Elmsleigh surface level car park. It crosses the entrance to the car park and also the access ramp to the Elmsleigh multi-storey car park. It also crosses a pedestrian route into the town centre that gives access from the existing railway station and the east. |
| 5.2 |
Relevant Policies (Note: all references to policies are to the Spelthorne Borough Local Plan unless stated otherwise) |
| 5.2.1 |
Town Centre Development. Government planning guidance in Planning Policy Guidance Note (PPG) 6 advocates a range of positive policies to promote new development in town centres and to enhance their vitality and viability. Surrey Structure Plan policies also seek to focus development in town centres. Staines is recognised as a major all purpose centre and a focus for major commercial development. Borough Plan Policy S2 seeks to enhance the attractiveness of Staines as a shopping and business centre by encouraging retail development north of the High Street and/or an extension to the Elmsleigh Centre by implementing specific movement measures (the two way traffic scheme for South Street and Thames Street which is now complete and pedestrianisation of the High Street), undertaking environmental enhancement of the town centre as a whole, and generally resisting loss of retail floorspace. |
| 5.2.2 |
Business Development. Staines town centre is identified in the Structure Plan as an appropriate location for business development and Policy EM4 sets out criteria for considering such development within the defined Commercial Area. |
| 5.2.3 |
Staines Station. Policy M2 seeks to improve the attractiveness of the existing station and its links to the town centre. Parking Policy. Policy M3 aims to maintain public car parking in the town centre at an appropriate level and Policy M4 gives priority in the management of car parking to provision for shoppers. The Council is committed to producing a more detailed parking management plan for Staines covering both public and private non-residential parking and complementary measures to encourage other modes. It is also committed, following public consultation, to the introduction of a Controlled Parking Zone for part of the town centre area. |
| 5.2.4 |
Cycling. Policy M13 sets out various measures to encourage cycling including providing cycle routes and requiring cycle facilities in new development. |
| 5.2.5 |
Design. Government guidance in PPG1 and PPG6 stresses the importance of good design both generally and in town centres. The Council expects new development to be of a high standard in terms of design and materials (Policy BE1). A number of specific criteria are identified that should be met including:-
|
| 5.2.6 |
Noise Policy. Borough Plan Policy (BE31) seeks to ensure that new development does not increase noise and/or vibration levels which would significantly affect adjoining areas. Detailed guidance on noise impact for development adjoining railways based on Government guidance in PPG24 is contained in Appendix 6 of the Plan (reproduced in this brief at Appendix A). |
| 5.2.7 |
Crime Prevention. The Council seeks to ensure crime prevention measures are incorporated in new development (Policy BE28). |
| 5.2.8 |
Archaeology. The northern part of the chord lies within an Area of High Archaeological Potential in which the Council requires the archaeological value to be assessed and if necessary an excavation to be carried out, before development is commenced (Policy BE25). |
| 5.3 |
Issues |
| 5.3.1 |
Major issues that will need to be assessed for the Staines Chord section are:-
|
| 5.3.2 |
The Council will also expect an archaeological assessment to be carried out. |
| 5.4 |
Potential Opportunities |
| 5.4.1 |
Opportunities arising from the Staines chord include:-
|
| 6. |
THE WINDSOR LINE SECTION |
| 6.1 |
Description |
| 6.1.1 |
The proposed route is shown on Plan 5, which also highlights issues and opportunities in this section. |
| 6.1.2 |
The Airtrack scheme follows the Windsor Line from Staines High Street, through the northern part of Staines and across the Staines bypass. The route is elevated in Staines Town Centre but drops to ground level before it reaches the bypass. |
| 6.1.3 |
No new sections of track are proposed in this section but two substantial changes are proposed:-
|
| 6.1.4 |
In the town centre the line runs on an embankment with the recently completed Two Rivers shopping centre to the west and the older Renshaw Industrial Estate to the east. Further north to the east of the railway lies the Moormede residential area, while to the west of the railway there is housing on Moor Lane and adjoining roads. |
| 6.1.5 |
South of the bypass the railway leaves the built up area, and passes the Moormede public open space and Common Land forming part of Staines Moor. The route of the old Staines West branch line lies immediately to the west of this section. |
| 6.1.6 |
A public footpath giving access to Staines Moor from the town centre crosses the line at grade and an access track to Staines Moor bridges over the line. |
| 6.2 |
Relevant Policies |
| 6.2.1 |
The policies referred to in Section 5.2 above regarding town centre development, business development, Staines station, parking policy, cycling, design, noise policy, crime prevention and archaeology are all relevant. In addition the following policies are also relevant. Transport Policies
|
| 6.2.2 |
Access for Disabled People. Policy SC3 seeks to secure improved access arrangements for people with disabilities by measures that include ensuring development proposals are accessible. |
| 6.2.3 |
Loss of Existing Housing. Policy H3 opposes the loss of residential land and buildings other than in exceptional circumstances. |
| 6.2.4 |
Loss of Existing Employment Land. Policy EM2 seeks to retain existing appropriately sited employment land. |
| 6.3 |
Issues |
| 6.3.1 |
For the Station. (See also comments in para 6.1.3 on the need for the station) Major issues that will need to be addressed are:-
|
| 6.3.2 |
For the Increased Use of the Line The main issues are:-
|
| 6.4 |
Potential Opportunities |
| 6.4.1 |
Opportunities arising from the station include:-
|
| 7. |
THE STAINES MOOR SECTION |
| 7.1 |
Description |
| 7.1.1 |
The proposed route is shown on Plan 6, which also highlights issues and opportunities in this section. |
| 7.1.2 |
North of Staines Airtrack continues to follow the Windsor line crossing beneath the Staines bypass. It then turns north to generally follow the route of the old Staines to West Drayton line across Staines Moor until it reaches the M25 at the northwest corner of Staines Moor. |
| 7.1.3 |
The form of the junction with the Windsor line is still to be determined. It may either be at-grade or grade separated on the northbound line only. The latter option would entail constructing a third line to the southwest of the existing track which would rise to bridge over the Windsor line at the junction. |
| 7.1.4 |
The new track would have up to 12 trains per hour in each direction. |
| 7.2 |
Relevant Policies |
| 7.2.1 |
Green Belt. The whole of the Airtrack corridor north of Staines lies within the Green Belt. Government guidance in PPG2 states that within Green Belts there is a presumption against inappropriate development that would conflict with the purposes of the Green Belt and maintaining its openness (see also Borough Plan Policy GB1). |
| 7.2.2 |
PPG2 also states that where any large scale development occurs in the Green Belt (including infrastructure development) it should contribute so far as possible to the achievement of Green Belt objectives which include:
|
| 7.2.3 |
Colne Valley Park. The whole of the Airtrack corridor north of Staines also lies within the Colne Valley Park which follows the Colne Valley from Staines to Rickmansworth. The Council supports the strategy for the Park which aims to promote environmental enhancement and recreational opportunities in a countryside setting (see Policy RU23). Nature Conservation. The new track across Staines Moor lies within the Staines Moor Site of Special Scientific Interest (SSSI). In line with Government Guidance on nature conservation (PPG8) Borough Plan Policy RU10 maintains a presumption against development within or affecting an SSSI, unless it can be demonstrated that there will be no material harm, either direct or indirect, to the ecological interest of the site. |
| 7.2.4 |
The track also passes close to the Southwest London Reservoirs Special Protection Area (SPA) and Ramsar site, designated in recognition of its international importance for birds. This includes the King George VI and Wraysbury Reservoirs. Policy RU10 requires the environmental effects of development proposals that may affect such designated sites to be rigorously examined. |
| 7.2.5 |
Where development proposals affect the nature conservation value of a site Policy RU14 requires the applicant to demonstrate that the benefits of the development outweigh the harm, that damage to nature conservation interest has been minimised and that mitigation and/or compensation has been provided including measures to monitor effectiveness. |
| 7.2.6 |
Landscape Policy. The section of Airtrack across Staines Moor lies within an Area of Special Landscape Character. Policy RU2 seeks to resist development adversely affecting the landscape character of such areas. It also expects new development to preserve or enhance landscape character and ensure that the scale and quality of open space and any features important to the area are protected. |
| 7.2.7 |
Common Land. Staines Moor is designated as Metropolitan Common. The Common includes land south of the bypass, which lies outside the SSSI, while the old railway embankment and some of the land between it and the M25, is not Common Land. Policy RU16 commits the Council to protect and conserve Metropolitan Common and to resist development that would result in the loss of common or harm its value. It also gives encouragement to schemes to maintain and enhance the value of such areas. |
| 7.2.8 |
Flood Policy. Land either side of the existing Windsor line south of the proposed junction is liable to flood and flooded extensively in 2000/2001. North of the junction, land to the east, and some land to the west is liable to flood but the embankment itself it excluded. Policy BE29 opposes development in areas liable to flood unless it complies with specific criteria set out in the policy. Government guidance in PPG25 requires developers to carry out a flood risk assessment where development is proposed in areas liable to flood. |
| 7.2.9 |
Existing and Proposed Rights of Way. Policy R9 seeks to safeguard existing rights of way and commits the Council to take opportunities to extend or create footpaths, bridleways and recreational cycle routes. This is supported by a Proposal (P35) for a bridleway route around the edge of Staines Moor which creates a circular route by connecting with the existing Moor Lane bridleway, Stanwell Moor Village and the route alongside the King George VI Reservoir. The line of the old railway embankment forms part of this proposal. |
| 7.2.10 |
Noise Policy. See para 5.2.7 |
| 7.2.11 |
River Corridors. Part of the Staines Moor section is close to the Wraysbury River corridor. Relevant policies are covered in the Stanwell Moor section of this Brief. |
| 7.3 |
Issues |
| 7.3.1 |
The Staines Moor section is particularly sensitive from the perspective of potential environmental impacts and great care will need to be taken in designing the scheme to minimise harm and provide mitigation. Ecological surveys of the area affected will be required. |
| 7.3.2 |
The main issues that will need to be addressed are:
|
| 7.4 |
Potential Opportunities |
| 7.4.1 |
Some harmful environmental impact from the route across Staines Moor will be inevitable. Under the Countryside and Rights of Way Act (2000) public bodies, are required to take reasonable steps, consistent with the proper exercise of their functions, to further conservation and enhancement of the special features on a SSSI, where these functions affect an SSSI. The Council will, therefore, expect to see a significant package of measures developed including mitigation of potential impacts and compensatory measures to provide positive improvements to the area. However, ancient, unimproved, species rich grassland cannot be replaced. |
| 7.4.2 |
Opportunities that should be examined include:-
|
| 8. |
THE STANWELL MOOR SECTION |
| 8.1 |
Description |
| 8.1.1 |
The proposed route is shown on Plan 7 which also highlights issues and opportunities in this section. |
| 8.1.2 |
North of Staines Moor the Airtrack route runs alongside the M25 adjacent to the Wraysbury River and the Moor Lane bridleway. It passes to the west of the Hithermoor gravel pit which is now being restored, and further north, to the west of Stanwell Moor village. |
| 8.1.3 |
The line runs initially at existing ground level but then drops below ground level as it approaches Junction 14 of the M25 and passes under Airport Way. It remains in tunnel for the approach to the airport. |
| 8.2 |
Relevant Policies |
| 8.2.1 |
The Airtrack corridor lies within the Green Belt, the Colne Valley Park and an Area liable to flood. It also adjoins a bridleway. Relevant policies on these issues are identified in section 7.2. |
| 8.2.2 |
General Landscape Policies. Policy RU1 seeks to protect and enhance the landscape of the Borough by measures that include seeking in development proposals to retain features that contribute positively to the landscape and by requiring high standards of landscape design in development proposals (see also para 7.2.2 regarding guidance in PPG2 on retaining and enhancing landscapes in the Green Belt). |
| 8.2.3 |
River Corridors. Policy RU5 resists development that detracts from the landscape, nature conservation or recreational value of river corridors and commits the Council to seeking environmental improvements in considering development proposals affecting river corridors. |
| 8.2.4 |
Nature Conservation. The Airtrack Corridor includes Greenhams Fishing Pond which is designated as a Site of Nature Conservation Importance. Policy RU11 safeguards SNCIs from development that would harm their ecological value or where the requirements of Policy RU14 regarding development benefits, mitigation and compensation are not met. |
| 8.2.4 |
This section is also close to the SPA and Ramsar site (see para 7.2.5). |
| 8.2.6 |
Noise Policy Noise policy is relevant to the potential impact on housing in Stanwell Moor (see para 5.2.7) |
| 8.3 |
Issues |
| 8.3.1 |
The main issues that will need to be addressed are:-
|
| 8.4 |
Potential Opportunities |
| 8.4.1 |
Opportunities that should be examined include:-
|
| 9. |
CONSTRUCTION ISSUES |
| 9.1 |
Introduction |
| 9.1.1 |
The previous sections have primarily been concerned with the impact of Airtrack once it is completed but construction of the rail link will itself have the potential for substantial impact regardless of the impact of the completed scheme. Normally a much larger area is required for construction activity than for the completed facility. In the case of a linear route such as a railway the additional land take could be significant. |
| 9.1.2 |
It is essential that construction impact, including land take, is examined as part of the proposal. The Council will therefore expect the Environmental Impact Assessment that must accompany the application, to include a full assessment of the impact of construction work, including identification of the land required for construction. This needs to be based on fully developed construction proposals that should in themselves be developed with a view to minimising environmental impact. |
| 9.2 |
Issues |
| 9.2.1 |
Particular issues that need to be assessed in developing construction proposals and assessing the impact of construction activity are:
|
| 9.3 |
Potential Opportunities/Strategy |
| 9.3.1 |
The Environmental Impact Assessment should be accompanied by a Construction Strategy that should include:
|
| 9.3.2 |
The strategy should particularly seek to avoid:-
|
| 10. |
RELATED PROJECTS |
| 10.1 |
Introduction |
| 10.1.1 |
There are a number of other major projects in close proximity to the Airtrack corridor, particularly north of Staines. The development of the Airtrack proposal, and the assessment of its impact, needs to take account of these schemes. These divide into:
|
| 10.2 |
Completed and Committed Projects |
| 10.2.1 |
Relevant projects are:
Specific improvement proposals for land adjoining Junction 14 should be respected. |
| 10.3 |
Related Projects Under Development |
| 10.3.1 |
The major project under this heading is the Central Railways scheme. This is a proposal for a freight only rail scheme intended to run along the eastern side of the M25. The Government is currently considering whether to support the project by means of a Hybrid Bill. |
| 10.3.2 |
The relationship of the Central Railways route to Airtrack is shown on Plan 8. Central Railways follows the same corridor as Airtrack north of Staines Moor and in the Staines Moor section follows an adjacent route alongside the M25. |
| 10.3.3 |
It is understood that Central Railways would require two lines for its own operation which suggests that there may not be scope for sharing track with Airtrack. The consequence would be a four track railway alongside the M25 if both schemes were developed. Additionally it appears that limitations on the maximum gradient of Central Railways, coupled with the requirement for Airtrack to drop down to go into tunnel at Junction 14, could result in the tracks being at different levels which may add to the cumulative impact. |
| 10.3.4 |
While the Central Railways scheme remains a possibility the Airtrack assessment should consider both with and without Central Railways scenarios. The "with Central Railways" scenario should consider:-
|
| 10.3.5 | The scope for mitigating identified impacts should be examined and proposals developed in discussion with the Central Railways promoters. |